Route 66 construction almost complete
Sep 16, 2016 12:03 pm
Katie Kocijanski reports in The Register-Star that Route 66 between Healy Boulevard to Route 9H may be back, at least with one-way traffic, next month. Workers have been replacing a bridge over the Claverack Creek for months on what was a busy thoroughfare, now with a slow detour northbound. “The bridge is still scheduled to be open by late October, with the possibility of occasional lane closures with alternating traffic during November,” DOT Public Information Officer Gina M. DiSarro said. “The deck was poured last week and left to cure, work is expected to resume on Monday.” Read the full story in The Register-Star.